Do not begin any earth-moving work until your Grading Permit is paid for and issued! When your Grading Permit is issued, you will receive written conditions regarding the requirements for erosion control measures and inspections. Please take note that all grading activities must be completed between April 15 and October 15.
Unpermitted Grading
If grading is performed without a permit, the property owner will be required to obtain a permit, even if the grading is completed. No further grading will be allowed during the permitting process.
Grading fees will be doubled.